As on 31/7/2019 4th Floor Roof Shuttering & Steel Work Going On
As on 30/6/2019 4th floor roof under construction
As on 30/6/2019 3rd Floor Roof Completed
As on June 30 D flat 3rd Floor Roof Slab Concrete Completed
As on 30/5/2019 C Flat 2nd Floor Roof Slab Shuttering Ongoing
An on 30/5/2019 Roof Top Front Side Column Concrete
As on 22/4/2019 First floor columns nearing completion
As on 22/4/2019 Upto 3rd floor roof casting completed.
As on 8-3-2019
As on 8-3-2019 4th floor work ongoing
As On 31-01-2019
28-11-2018 1st Floor Slab Casting Work Completed
As On 15-02-2018
As On 14-12-2017